Group Project Status
Report Guidelines
(Updated
8/27/07)
Group Status Report & Project Plan
Each Monday by 5 PM each group leader should submit a weekly status report and the current Microsoft Project Group Project Plan to the WebCT Group Project assignment area.
The MS Project file should have actual work performed by each member input to the appropriate task through Sunday.
The Group Status Report should state the overall project status of either "Ahead" or "Behind" (there is no "OK" status).
This report should also give pertinent accomplishments, plans for the next week and issues for the week. Example:
|
Group Status Report for Group Retrofit for Week ending 9/16/07Overall Status: BehindGroup Hours Worked: 11 (4 in class/7 outside) Accomplishments
Plans for next week: Issues: |
Naming conventions (Examples for Group R)
Weekly Report: WR_091105_GroupR.doc (use Sunday date for week ending)
MS Project file: PP_091105_GroupR.mpp (copy and rename for submission – Please save in MS Project 2003 format)